An aerial view shows construction progress on Dry Dock 5 (P-209) at Joint Base Pearl Harbor-Hickam, Hawaii, Nov. 9, 2026. Officer in Charge of Construction Pearl Harbor Naval Shipyard oversees the project as part of the Navy’s Shipyard Infrastructure Optimization Program to modernize Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility. (U.S. Navy photo by DHO Joint Venture Released)

The Officer in Charge of Construction Pearl Harbor Naval Shipyard (OICC PHNSY) reports that crews placed more than 600 cubic yards of concrete in November for beams that will support the portal crane rails and foundations for the west electrical substation.

Crews continued to place more than 900 cubic yards of concrete at depths of 40 to 60 feet as part of construction on the main dry dock foundation. They also began installing ballast in the dry dock basin. The added weight will help hold the prefabricated floor units in place once dewatering begins.

Work also began on the water storage tanks for the dry dock’s Fresh Water Fire Pump House. Each completed tank will hold more than 80,000 gallons of usable water.

Enable Notifications OK No thanks