Amur Shipyard Begins Mooring Trials of Project 20380 Rezkiy

At the acceptance base of the Amur Shipyard (ASZ, part of the United Shipbuilding Corporation) in Vladivostok, mooring trials have begun on the fourth serial multipurpose patrol ship of project 20380 “Rezkiy”.

All systems and equipment of the ship are ready for testing. A schedule for closing mooring certificates has been drawn up.
All the mechanisms of the corvette were installed in the regular places, life support and control systems were mounted. All types of power supply are accepted for the main distribution boards.

To carry out tests and commissioning works, a commissioning team was formed from workers of the mechanical and electrical installation industries, pipe processing and slipway shops with the participation of specialists from the testing department and representatives of contractor organizations.

The fourth in a series of project 20380 corvettes, being built at the NPP under a contract with the Ministry of Defense, left the water area of ​​the Amur shipyard in Komsomolsk-on-Amur on October 5 this year. Having passed more than a thousand kilometers along the Amur and the Tatar Strait to the Sea of ​​Japan, TSD “Zeya” with a corvette on board in the last ten days of October safely reached the delivery base of the ASZ.

According to Razhden Baratashvili, the responsible deliverer of the Rezkiy corvette, the work on the corvette is proceeding in accordance with the construction schedules, and if the contractors-suppliers fulfill their obligations, the ship will be handed over to the customer next year.